COPPER 360 LIMITED - Short form announcement: operational overview, reviewed condensed consolidated provisional financial results

Release Date: 31/05/2023 17:20
Code(s): CPR     PDF:  
Wrap Text
Short form announcement: operational overview, reviewed condensed consolidated provisional financial results

Copper 360 Limited
(Formerly Big Tree Copper Limited)
(Incorporated in the Republic of South Africa)
Registration number 2021/609755/06
JSE Share Code: CPR ISIN: ZAE000318531
(“Copper 360” or “the Company”)


SHORT FORM ANNOUNCEMENT: OPERATIONAL OVERVIEW, REVIEWED CONDENSED
CONSOLIDATED PROVISIONAL FINANCIAL RESULTS FOR THE YEAR ENDED 28 FEBRUARY
2023 AND REVIEW CONCLUSION

OPERATIONAL OVERVIEW
Highlights
•       Successful commissioning of SX/EW copper processing plant and first commercial production.
•       Volume treated compared to the previous period increased by 296% to 67,045 tons (2022:
        16,934t).
•       Copper sold increasing by 191% to 284 metric tons sold compared to previous period (2022:
        98Mt).
•       Productivity increased by 97% to 462 milled tons per person (2022: 235t/man) despite a 101%
        increase in total labour compliment to 145 people (2022: 72 people).
•       Ex-works LME price impact as result of ZAR: USD exchange rate staying effectively constant in
        terms of ZAR copper price received despite a 11,66% decrease in the LME copper price
        comparable to the previous reporting period.
    Description                    Unit                     12 months          *5 Months    Percentage
                                                      28 February 2023   28 February 2022       change
    Statistical information
    Tons milled                    Metric tons                 67 045             16 934         296%
    Delivered grade                % copper                     0.88%              1.38%         -36%
    Total plant recovery           %                              48%                56%         -14%
    Recovered copper               Metric tons                  284.7                98.0        191%
    Number of people employed      N                              145                 72         101%
    Tons milled per total labour   Mill tons/person            462.38             235.19          97%
    complement
    Copper tons sold per labour    Copper metric                  1.96               1.36         44%
    complement                     tons/person
    Average copper price           R/metric ton                117.13             123.88         -5.4%
    received
    Average exchange rate          ZAR:USD                      16.54              15.41          7.3%
    Average LME copper price       USD/metric ton               8 676                766        -11.2%
    Average USD copper price       USD/metric ton               7 082              8 039        -11.9%
    received
    Discount to LME for ex works   USD/metric ton                1 594              1 727        -7.7%
    (USD)
    Discount to LME for ex works   ZAR/metric ton              26 365               6 613        -0.9%
    (ZAR)
    Discount as percentage of      %                            18.4%              17.7%         3.9%
    LME

    **Reviewed financial information
    Revenue                        R’000                        33 348             12 140       174.7%
    Operational profit/(loss)      R’000                      (80 707)           (21 287)       279.1%
    Other income                   R’000                         2 213             31 154       -92.9%
    Operating profit/(loss)        R’000                      (78 494)              9 867      -895.5%
 Loss per share (EPS)             Cents                                    (38.9)                        7.0      -655.7%
 Headline loss per share
 (HEPS)                           Cents                                    (37.6)                     (16.6)      -126.5%
 * Production only started in August 202, resulting in only 5 months of trading for the period ended 28 February 2022
  ** The Auditors’ review of the Provisional Results does not extend to the statistical information in this table


The financial year ended 28 February 2023 includes 12 months of production compared to only 7
months of production for the period ended 28 February 2022 with first copper production, as part of
plant commissioning, starting during August 2021 and ending January 2022. First commercial
production (post commissioning) started during February 2022 with first copper sales recorded during
October 2021. Tons milled for the financial year under review increased by 296% to 67 045 tons
compared to the prior period (2021: 16 934t) with copper grade decreasing by 36% from 1.38% to
0.88%. This resulted in copper recovered and sold increasing by 191% to 284.7 metric tons compared
to the previous reporting period (2021: 98 Mt). During the financial year under review the operation
changed from a filter press to a Fines Optimised Heap Leach (“FOHL”) process during July 2022 to
September 2022 to improve both volume throughput and achieve cost reductions in terms of copper
leaching. Volume throughput per month increased by 400% from approximately 2 000 milled tons to
10,000 milled tons as a result of the change to the FOHL dams. Copper recoveries however decreased
by 14% (2023: 48%) from 56% during the previous reporting period. Despite the decrease in recoveries
the resultant increase in volume more than made up for the lower copper recovery.

A major impact during the current reporting period was a decrease of 36% in the delivered grade from
1.38% (2023: 0.88%) compared to the previous reporting period. This was the result of the initial high
grade (in situ grades of between 1.2% and 1.6% Cu) ore stockpiles at Nababeep (where the processing
plant is located) being depleted and only lower grade stockpiles remaining (in situ grades of between
0.6% and 1% Cu). Management in terms of grade flexibility (by having different grade stockpiles for
mixing to deliver optimum feed grade) was impacted by the original crushing system not being
adequate and having to be replaced by contract screening and crushing. This issue has been resolved
with (a) the acquisition post period of a R30 million new crushing plant that will be operated “in-
house” and (b) addition of higher-grade stockpiles from the Carolusberg and Jubilee sites (in situ
grades varying between 1% and 3.5% Cu). The new crushing plant will have an increased monthly
processing capacity of 100 000 tons compared to the current crushing capacity of 30 000 tons per
month. This will not only allow for better stockpile management but also cater for the ore that will
feed the new floatation processing plant being constructed.

Average effective copper price received decreased by 5.44% to ZAR117k/Mt of Copper metal sold
(2022: ZAR123k/Mt). Although the LME copper price decreased by 11.16% to USD8 676/Mt compared
to the previous period (2022: USD9 766/Mt) the ZAR: USD exchange rate improved during the same
comparable period by 7.33% to 16.54 (2022: 15.41). This reduced the impact in terms of the discount
to LME price received ex-works by only 0.93% to ZAR26 364 compared to ZAR26 613 received during
2022.

The operating loss increased by 279% to ZAR80.7 million compared to the previous period (2022:
ZAR21.287 million). Revenue increased by 174% to ZAR33.4 million compared to ZAR12.1 million in
2022. It should however be noted that the previous reporting period included other income related
to the sale of revenue sharing royalty agreement of ZAR31.154m. Operating expenses increased by
241.6% during the financial year to R114.1 million compared to ZAR33.4 million during 2022. The
increased operating loss was a result of
a) Fixed expenses being incurred for 12 months compared to 5 months in the prior period,
b) commissioning costs,
c) contract crushing,
d) plant stoppage as result of the solvent extraction circuit having to be restocked and safety
     stoppages,
e)   loadshedding - the operations have been and continue to be hampered by the current load
     shedding regime. This has effectively resulted in it only being able to operate at 50% of its
     capacity, principally as a result of diesel generator backup failures due to frequent loadshedding
     occurrences, and
f)   the second mill arriving 4 months late due to COVID 19-related logistics bottlenecks and thus
     impacting on production output.

Subsequent to the capital raising accompanying the listing of Copper 360 on 21 April 2023, several
investments have been committed to that will address the root causes of operating losses. These
include:
a) the acquisition of an owned crushing plant that will replace the current crushing contractor. This
     plant has been ordered and will be installed during June 2023. The plant will also crush the ore
     feed from the sulphide ore projects that are currently being developed elsewhere in the group,
b) further backup generator capacity is currently being installed and it is expected that it will enable
     CCOC to increase its copper output from July 2023, and
c) the introduction of thickeners that will supplant the FOHL process and increase the recoveries
     from current levels of around 50% to in excess of 80%, which will result in increased copper
     output.
Pursuant to the above, it is expected that the forecast copper production for the financial year
ending 29 February 2024 contained in the Pre-listing statement will be achieved.

REVIEWED FINANCIAL INFORMATION
                                28 February 2023 28 February 2022                       Percentage
 Revenue                                   33 348          12 140                         +174.7%
 Operating profit                        (78 494)           9 867                          -895.5%
 Loss per share (EPS)                       (38.9)             7.0                         -655.7%
 Headline loss per share (HEPS)             (37.6)          (16.6)                         -126.5%

REVIEW CONCLUSION
The auditors, Moore Pretoria (“Moore”), has issued an unmodified review conclusion on the reviewed
condensed consolidated provisional financial results for the year ended 28 February 2023.
The auditors report issued on the provisional consolidated financial statements and the actual
provisional consolidated annual financial statements can be accessed at: www.copper360.co.za.


SHORT FORM ANNOUNCEMENT

This short form announcement is the responsibility of the directors and is only a summary of the full
announcement released on SENS on 31 May 2023.
This short form announcement does not contain full or complete details pertaining to the Company’s
results. Any investment decisions by investors and/or shareholders should therefore be based on
consideration of the full announcement which may be downloaded from the Company’s website at
www.copper360.co.za and may be viewed at the registered offices of the Company and of the
designated advisor, or is available electronically by sending a request to micel@copper360.co.za, at
no charge, during normal business hours for a period of 30 days after the release of this
announcement. The full announcement is also available on the JSE’s website at
https://senspdf.jse.co.za/documents/2023/jse/isse/CPRE/FY2023.pdf
This short-form announcement itself is not audited or reviewed.
Stellenbosch

31 May 2023

Designated Advisor: Bridge Capital Advisors (Pty) Ltd

Date: 31-05-2023 05:20:00
Produced by the JSE SENS Department. The SENS service is an information dissemination service administered by the JSE Limited ('JSE'). 
The JSE does not, whether expressly, tacitly or implicitly, represent, warrant or in any way guarantee the truth, accuracy or completeness of
 the information published on SENS. The JSE, their officers, employees and agents accept no liability for (or in respect of) any direct, 
indirect, incidental or consequential loss or damage of any kind or nature, howsoever arising, from the use of SENS or the use of, or reliance on,
 information disseminated through SENS.