To view the PDF file, sign up for a MySharenet subscription.

SOUTHERN PALLADIUM LIMITED - Quarterly Activities Report for 31 December 2024

Release Date: 31/01/2025 09:30
Code(s): SDL     PDF:  
Wrap Text
Quarterly Activities Report for 31 December 2024

Southern Palladium Limited
Incorporated in the Commonwealth of Australia
Australian Company Number 646 391 899
ASX share code: SPD
JSE share code: SDL
ISIN AU0000220808


31 January 2025
                                              Quarterly Activities Report for 31 December 2024
ASX:SPD, JSE:SDL
                                              DECEMBER QUARTER HIGHLIGHTS
ACN: 646 399 891
                                              Operational:

Corporate Directory                       •   Completion of additional Resource Estimate upgrade for SPD's flagship 70%
                                              owned Bengwenyama Platinum Group Metal (PGM) project, resulting in a
Executive Chairman                            total combined UG2 and Merensky Reef Mineral Resource ounces (Measured,
Roger Baxter                                  Indicated and Inferred) of 40.25 Moz.
                                          •   The Measured and Indicated Mineral Resource for the UG2 and MR on a 7E
Managing Director                             basis is now 10.39Moz ounces.
Johan Odendaal                                
                                          •   Mining Right Application submitted 29 September 2023. Decision by the
Non-Executive Directors                       DMRE anticipated early Q2 2025.
Mike Stirzaker
Rob Thomson
Daan van Heerden                          •   Completion of Prefeasibility Study (PFS) for the Bengwenyama PGM project,
Lindi Nkosi-Thomas                            which resulted in highly attractive economics justifying development of the
                                              project. Highlights of the PFS included:
                                              • Post-tax ungeared NPV8% (real) of USD1.059 billion, based on conservative
Company Secretary                               long term commodity price assumptions (Pt US$1200/oz, Pd US$1100/oz,
Andrew J. Cooke                                 Rh US$6,200/oz).
                                              • Life of mine (LoM) from the UG2 reef alone estimated at 29 years with a
Top 5 Shareholders                              total of approximately 45 million tonnes mined (~8.88 Moz 6E*) for an
                                                average annual steady state saleable product of 400Koz PGM (6E basis*)
Nicolas Daniel Resources Pty Ltd              • Cash costs firmly at the low end of the global cost curve - a result of high
Nurinox Investments Pty Ltd                     delivered grade and shallow mining depths.
Robert Napier Keith                           • Strategic location on the Eastern Limb of the Bushveld Complex, in
Legacy Platinum Corporation                     proximity to other Tier 1 operations owned by major mining companies.                   
HSBC Custody Nominees (AUS) Ltd               • LoM EBITDA totalling ~USD5.6 billion with a post-tax IRR of ~28%; post-                 
                                                tax capital payback of ~3.5 years from first concentrate production.                              
Company Overview                                 

Dual-listed platinum group metal              Corporate:
(PGM) company developing the
advanced Bengwenyama PGM                  •   During the quarter, Mr Roger Baxter assumed the role of Executive Chairman
project, particularly rich in             •   With a modest quarterly cash burn rate (December quarter: A$1.07 million)
palladium/rhodium, located in South           and a strong cash balance of A$3.65 million at quarter end, Southern
Africa's prolific Bushveld Complex.           Palladium is well funded for multiple quarters as it advances key project
                                              development work streams, pursues offtake negotiations and advances
Contact:                                      project development funding opportunities
E: info@southernpalladium.com             •   Cash balance of A$3.65 million excludes cash held by the Company's 70%
W: www.southernpalladium.com                  subsidiary, Miracle Upon Miracle Investments (Pty) Limited at 31 December
                                              2024 of A$0.43 million (30 September 2024: A$0.39 million).


Southern Palladium Executive Chairman, Roger Baxter commented: "The December quarter was defined by
Southern Palladium's transition from explorer to mine developer at our flagship Bengwenyama PGM project,
following the release of a detailed Pre-Feasibility Study in October. The PFS was highlighted by a post-tax valuation
of over US$1bn and marked the culmination of a comprehensive and highly successful 2-year drilling exploration
program. Additional drill results in the quarter added to what is now a significant PGM resource, and confirmed the
project's standing as one of the premier remaining development opportunities in the Bushveld Complex. As we
transition to mine development, the Board considers there are now multiple opportunities to unlock
considerable value as we advance funding and offtake discussions alongside project development workstreams.
With a strong cash balance at quarter-end, Southern Palladium is comfortably positioned to advance these
discussions over the course of 2025 in pursuit of our stated development strategy."

Southern Palladium (ASX: SPD, "Southern Palladium" or the "Company") is pleased to announce its quarterly
activities summary for the three months ended 31 December 2024.

The Company's primary focus during the quarter was the ongoing advancement of its development programme at
the Bengwenyama PGM (platinum group metals) project, in which it holds a direct 70% stake. The project is
strategically positioned in the heart of the world class Bushveld Complex – the largest source of PGMs globally – in
a significant underground mining region with established expertise and infrastructure.

Note:
7E or 6E+Au in this document refers to platinum, palladium, rhodium, ruthenium, iridium, osmium and gold.
6E or 5E+Au refers to platinum, palladium, rhodium, ruthenium, iridium and gold and;
4e or 3E+Au refers to platinum, palladium, rhodium and gold

Overview of December Quarter Activities

Resources and Reserves

Mineral Resource Upgrade

During the quarter, the mineral resource for the Merensky Reef (MR) MRE was upgraded and now totals 15.44Moz.
As shown in the table below, the total combined Mineral Resource (M&I and Inferred) is now 40.25Moz.

The Measured and Indicated Mineral Resource for the UG2 and MR on a 7E basis is now 10.39Moz ounces with a
combined (7E & 4E) Inferred Mineral Resource of 29.86 Moz. (17.43Moz (7E) for the UG2 and MR + 12.43Moz (4E)
for the UG2 and MR. The total combined Mineral Resource for the UG2 and MR as at 23 October 2024 is
summarised in Table 1. (refer ASX Announcement 23 October 2024)

The latest MR upgrade has estimated an Indicated Mineral Resource of 2.23 Moz at a 6PGE + Au grade (7E) of 2.76
g/t respectively over 202 cm. This is a 17% increase in the M&I from the previous MR release. In addition to the
increase in the Indicated Resource, there has been a 54% increase in the MR Inferred Mineral Resource from 8.60
Moz to a combined inferred MR Mineral Resource of 13.21 Moz (7.13 Moz + 6.08 Moz). As per the UG2 Inferred
Mineral Resource increase (refer ASX Announcement 27 August 2024), this is also largely due to the conversion of
the exploration target in the western area of the Project (Nooitverwacht) to an Inferred Mineral Resource arising
from the additional historical data sourced.

An Inferred Mineral Resource has a lower level of confidence than that applied to an Indicated Mineral Resource
and cannot be converted to an Ore Reserve. It is reasonably expected that the majority of the Inferred Mineral
Resource could be upgraded to an Indicated Mineral Resource with continued exploration.

Table 1: Combined UG2 and MR Mineral Resource as at 23 October 2024

                              Tonnes Thickness          Pt       Pd     Rh     Au        Ir   Os     Ru      4E      7E      Cu           Ni
              Resource                                                                                                                          Moz       Moz    Total
  Reef                         Mt          (m)                                        (g/t)                                        (%)
              Category                                                                                                                          (4E)      (7E)   Moz1
Merensky       Indicated      25.11        2.02        1.62     0.64    0.10   0.12    0.03   0.03   0.21   2.49    2.76    0.04         0.12   2.01      2.23   2.23
Merensky     Inferred (7E)    62.54        1.81        2.09     0.86    0.14   0.18    0.04   0.04   0.26   3.22    3.55    0.05         0.14   6.47      7.13   7.13
Merensky      Total (7E)      87.66        1.87        1.96     0.80    0.13   0.16    0.04   0.04   0.24   3.01    3.32    0.04         0.13   8.48      9.36   9.36
Merensky     Inferred (4E)    59.44        1.96        2.01     0.93    0.10   0.17                         3.18                                6.08             6.08
Merensky      Total (4E)     147.10        1.90        1.98     0.85    0.11   0.17                         3.08                                14.56            15.44
  UG2         Measured        7.17         0.77        3.69     3.75    0.76   0.12    0.25   0.17   1.24   8.34    10.00   0.03         0.16   1.92      2.30    2.3
  UG2          Indicated      18.52        0.72        3.68     3.63    0.76   0.11    0.26   0.17   1.23   8.19    9.85    0.04         0.16   4.88      5.86   5.86
  UG2        Inferred (7E)    33.01        0.69        3.67     3.50    0.76   0.11    0.26   0.17   1.23   8.04    9.70    0.04         0.17   8.54      10.30  10.3
  UG2         Total (7E)      58.70        0.71        3.67     3.57    0.76   0.11    0.26   0.17   1.23   8.12    9.78    0.04         0.17   15.33     18.46  18.46
  UG2        Inferred (4E)    36.12        1.30        3.00     2.01    0.44   0.07                         5.47                                6.35             6.35
  UG2         Total (4E)      94.82        0.93        3.42     2.98    0.64   0.10                         7.11                                21.68            24.81
   Combined Total (7E)       146.35        1.40        2.64     1.91    0.38   0.14    0.13   0.09   0.64   5.06    5.91    0.04         0.14   23.81     27.82
   Combined Total (4E)       241.92        1.52        2.54     1.68    0.32   0.14                         4.66                                36.24
 Combined Total (7E&4E)1                                                                                                                                         40.25
        
Note:
1. Several historic drill holes in the Nooitverwacht Extension area did not assay for the minor PGEs, so a 7E resource cannot yet be stated
   for part of the inferred Mineral Resource. However, it does contribute to the total resource ounces.
2. All elements have been estimated individually and their combined grade will vary slightly from the estimated composite 4E and 7E
   modelled grades.
3. Several historic drill holes in the Nooitverwacht Extension area did not assay for the minor PGEs, so a 7E resource cannot yet be stated
   for part of the inferred Mineral Resource. However, it does contribute to the total resource ounces.
4. All elements have been estimated individually and their combined grade will vary slightly from the estimated composite 4E and 7E
   modelled grades.

                                                                                                                                                        
Bengwenyama Maiden JORC Probable Reserve

The company declared a maiden reserve following the PFS study. The 6E Ore Reserves for the Project consist of
Measured and Indicated Resources from the UG2 reef only. The Ore Reserve classification was conducted by
converting Measured and Indicated Mineral Resources to Probable Ore Reserves.

Table 2 provides a detailed summary of the tonnage, grades and content for Probable Ore Reserves within the
Bengwenyama Project.

                                     Table 2: Ore Reserve Estimation as at 23 October 2024 (UG2 reef)
                           Tonnes       Pt     Pd         Rh     Au       lr        Os     Ru       4E        6E     Cu      Ni     Cr203   Moz(6E)
   Ore Reserve Category
                             Mt        (g/t)   (g/t)     (g/t)   (g/t)   (g/t)     (g/t)   (g/t)   (g/t)     (g/t)   (%)     (%)    (%)
        Probable             31.72      2.34    2.33     0.48     0.07    0.16        -     0.78    5.22      6.17    0.02   0.12   19.03     6.29
         Total               31.72      2.34    2.33     0.48     0.07    0.16        -     0.78    5.22      6.17    0.02   0.12   19.03     6.29
Notes:
1. The Ore Reserve estimation included diluted Measured and Indicated Mineral Resources only.
2. No Inferred Mineral Resources have been included in the Ore Reserve.
3. The Ore Reserve estimation was completed using a 6E basket price (before payabilities) of USD1,557/oz over the LoM.

Bengwenyama Project Prefeasibility Study

The Prefeasibility Study completed during the quarter confirmed the commercial viability of the Bengwenyama
project. (refer ASX Announcement 28 October 2024).

The key study results of the Scoping Study are detailed in the below table. The results indicate an economically
viable project with a post-tax NPV8% of US$1.06bn and a post-tax IRR of 28%. The payback period has been
calculated as 3.5 years from start of first plant throughput. The Project has an all-in-sustaining-cost of US$800/6E
oz. Project cashflows are assessed on a real, pre-finance basis.

Source:
1. ASX Announcement 28 October2024
2. Note: Indicative NPV ignores residual value beyond modelled life or any exploration upside and hence is not considered.
3. 6E – Platinum, Palladium, Rhodium, Ruthenium, Iridium + Au

The Prefeasibility Study identified that there is a well-established downstream smelting and refining process for
PGM concentrates within South Africa. Well-established precedents exist for commercial terms that would be
applicable for UG2 and Merensky concentrates. Most smelters processing the concentrate from the Eastern and
Western Limbs are situated in Rustenburg, with almost all the concentrator product in the area being transported
by truck to Rustenburg. The Project PGM concentrates are believed to be suitable for these facilities.
                                                                                                                                           
Physical Parameters
•    Development of a ~2.4 Mtpa UG2 reef two decline underground mining operation with mill feed head
     grade of 6.10g/t (6E) averaging over LoM.
•    Conventional flotation and spiral plant to deliver a marketable PGM concentrate (~85% recovery for PGM)
     and a 42% chrome concentrate for sale to export markets.
•    Initial Capital of ~USD385 million (including a 15% contingency).
•    Low LoM cash costs for operations of ~USD644/6E oz (~ZAR2,609/t).
•    LoM AISC of ~USD800/6E oz with a high LoM EBITDA Margin of ~50%.

Production Confidence Levels
•    Percentage of JORC Measured and Indicated Resources used in the PFS LoM diluted mine plan is 87%
     (Inferred 13%) over the first five years, 94% (Inferred 6%) over the first 10 years and 74% (Inferred 26%)
     over the estimated 29-year mine life.
•    Mine scheduling has targeted high grades initially from the shallow area of the UG2 reef with run of mine
     (RoM) at an average feed grade over the first 10 years of 6.3g/t (6E).
•    Average processing recovery of 85% over the life of mine from testwork demonstrates amenability to
     conventional processing technology adopted in the South African platinum industry.

Environmental Social Governance
•    Widespread community and Traditional Council engagement has been established.
•    Extensive environmental baseline studies have been completed across the Project Area.
•    Heritage clearances have been completed over the Project development and operations area.
•    Environmental Impact Assessment (EIA) was submitted on 11 July 2024, with the Department of Mineral
     Resources and Energy (DMRE) issuing an acknowledgment on 17 July 2024.
•    Additional applications for a Waste Management License (WML) will be submitted to manage waste products
     and geochemical hazards.
•    An Integrated Water and Waste Management Plan (IWWMP) has been initiated, as per GNR 267 of 2017, to
     regulate water use activities.
•    Closure costs for the LoM are estimated at R90.921 million (USD4.65 million) as of April 2024, compiled by
     OMI Solutions (Pty) Ltd.
•    Social and Labour Plan (SLP) has been developed in line with the Mining Charter and MPRDA requirements to
     support community development.
•    On September 29, 2023, Southern Palladium officially submitted its application for a Mining Right (refer ASX
     Announcement 2 October 2023), a decision by the DMRE is anticipated early Q2 2025.


Key PFS Outcomes and Assumptions

The PFS confirms that the Bengwenyama Project is a globally significant Tier 1 PGM Project and presents a
commercially viable development opportunity. A summary of the initial physical and financial evaluation of the
Project at a 2.4 Mtpa throughput rate is indicated in Table 3. The peak funding requirement is USD452 million
(inclusive of contingencies), with a pay-back period of 6.0 years from start of mining or 6.5 years from start of
construction. Early revenue growth was supported by a combination of higher measured resource grades, an
accelerated ramp-up that increased throughput (yielding more ounces), and a projected higher rhodium price. The
UG2 basket price of USD 1,557 per 6E oz is a conservative estimate considering the peak of USD 4,675 per 6E oz for
the UG2 basket price back in April 2021. More detailed information was gathered on the PFS labour costs. The
accuracy of the labour cost estimate has been significantly enhanced by reviewing and refining labour                                                                                                             
requirements, adjusting salary rates based on benchmarks from existing operations, and aligning job gradings with
industry standards.

Table 3: Key PFS Valuation Metrics

                                 Production Metrics                                Unit                             PFS
                                      Life of Mine                                 Years                             29
                          Life of Mine Ore Tonnes Mined                              kt                          45,262
                                    Processing Rate                                ktpa                           2,400
                              Total 6E Oz in Mine Plan*                             koz                           8,876
                            6E Grade Delivered to Plant                             g/t                            6.10
                                 6E Recovered grade                                 g/t                            5.18
                                      6E Recovery                                    %                              85%
                               Total 6E Oz Recovered                                koz                           7,545
                                  PGM Concentrate                                    kt                           1,987
                               Chromite Concentrate                                  kt                           6,083
                                  
                                  Financial Metrics
                                      Basket Price                              USD/6E oz                         1,557
                                    Exchange Rate                                ZAR/USD                          19.57
                          All In Sustaining Costs ("AISC")                      USD/6E oz                           800
                             Average AISC First 5 Years                         USD/6E oz                           829
                             Average AISC First 10 Years                        USD/6E oz                           843
                             Net free cashflow (pre-tax)                        USD million                       4,660
                            Net free cashflow (post-tax)                        USD million                       3,403
                                         EBITDA                                 USD million                       5,607
                        Payback Period from Ground Break                          Years                             6.5
                         Payback Period from First Mining                         Years                             6.0
                   Payback Period from First Plant Production                     Years                             3.5
                            Peak Funding Requirement                            USD million                         452
                                  NPV 8% (pre-tax)                              USD million                       1,562
                                  NPV 8% (post-tax)                             USD million                       1,059
                                      IRR (pre-tax)                                 %                               33%
                                     IRR (post-tax)                                 %                               28%
                                
                               Capital Cost Estimate
                                Initial Mining Capital                          USD million                          96
                                       Initial Plant                            USD million                         129
                                        Initial TSF                             USD million                          42
                                Initial Shared Capital                          USD million                          63
                  Total Initial Capital Excluding Contingencies                 USD million                         330
                            Initial Capital Contingencies                       USD million                          55
                                 Total Initial Capital                          USD million                         385
                    
                      Key Environmental and Social Statistics
                 Life of Mine State Royalties & Corporate Taxes                  USD million                      1,902
                              Life of Mine Expenditure                           USD million                      5,868
                      Life of Mine Total Economic Value Add                      USD million                      7,770



                                                                                                       
Mining Access and Schedule

For the PFS, production from the Bengwenyama Project is sourced only from the UG2 reef, and mainly on the
shallower farm, Eerstegeluk. The production profile demonstrates an annual production range of 2.4mtpa from
conventional underground stoping with a 1.0 m stoping width accessed through two decline access points, the early
access development and the primary access development. First reef to be accessed at vertical depth of just 50m.

The early access development will consist of a two-barrel, early access decline with a 5 m x 4 m decline and a
return airway with dimension of 4 m x 4 m, sunk at a slope of 1:10, providing access to the UG2 reef. This will
allow for optimal manoeuvrability of trackless equipment and extended tyre life. The primary access development
will also consist of a two-barrel decline with two 6 m x 4 m end sizes, sunk at a slope of 1:6;4, designated for
transport of men and material and a conveyor belt for the transport of ore and waste.

Figure 1: Decline Access Arrangement and Mine Design Areas

The selected mining method for the underground operations for the Bengwenyama Project is a hybrid approach
optimised for narrow reef orebodies, combining mechanised development with conventional stoping, typically
utilised by neighbouring mines Modikwa and Marula. This method enhances ore extraction while minimising
dilution, supporting the safety and efficiency of mining operations.

Figure 2: Mining Area in the UG2 Mineral Resource Category
                                                                                                         7
Ore production tonnes over the first five years is achieved with 87% coming from JORC Measured and Indicated
resource classifications and over the first 10 years coming from 94% JORC Measured and Indicated resource
classifications. JORC Measured and Indicated resources comprise 74% of the overall LoM ore production.
Downdip extensions to existing resources and mining of the Merensky Reef have the potential to keep PGM
production at steady state beyond year 19. The Mineral Resource category diluted LoM plan and cumulative
contribution by category is illustrated in Figure 3.

Figure 3: Mineral Resource Category Diluted Life of Mine Plan and Cumulative Contribution by Category

Processing

The Bengwenyama Project is located close to other, similar PGM operations. The Bushveld Complex has been
mined extensively for multiple decades for the extraction of PGM minerals from the UG2 reef. Standard
technology has been established and has been optimised with current state-of-the-art technology involving MF2
(2x Mill and Float process) processing infrastructure with an average recovery rate of 85%. Steady state saleable
product is estimated at just above 400,000 ozpa as illustrated in Error! Reference source not found.. Chrome is a
byproduct from the UG2 Chromitite seam and will add significantly to PGM revenue streams.

Figure 4: Annual Saleable Product - 6E

Source: Minxcon Scoping Study Update, February 2024

The tailings storage facility (TSF) is expected to have at least 45 Mt of storage capacity and a maximum height of
82 m, with the potential of expandability. The preliminary outcome from the tailings storage study favoured dry                                                                                                         
stacking. Despite the expectedly higher cost of implementing dry-stacking technology, the site is expected to
provide storage for the current LoM without having to expand outside of the mine lease boundary.

Mine Infrastructure and Services

The Project is accessed through a regional road (R555) and forms part of the established paved road network. The
R555 is the main route to the Project Area, which heads 27 km northeast from the town of Middelburg before
reaching the town of Burgersfort. A paved district road leads towards the Eerstegeluk farm - the location of the
Bengwenyama Project.

Figure 5: Project Infrastructure Layout

Power will be supplied to the Project through a 132 kV overhead lines connected to the national grid. A
transmission line running in close proximity to the Project (+- 3.5 km) is fed by the Merensky and Mampuru
transmission and distribution substations. Synchronised back-up generators will feed into the Bengwenyama
distribution substations.

A full load list has been drafted and early indications for the total installed power is estimated at 64.6 MW with a
power draw of 43.4 MW. An application has been submitted to Eskom (local power utility) on the 29th of August
2024, for the supply of power as well as obtaining the required cost estimate letter ("CEL") from the utility to
determine the detailed requirements to establish the access to the grid.

A study has been completed to assess potential carbon emission reduction strategies as well as alternative energy
solutions for the project. This included an energy needs assessment, resource and technology assessment, energy
modelling, local grid assessment and concept solar PV design. This will be further optimised and assessed during
the following study phase.
                                                                                                           
Process water will be sourced from the Lebalelo Water User Association, a local water supply authority supplying
water to local communities, neighbouring mining operations, and agricultural activities in the area. A Lebalelo
pipeline is located in close proximity (roughly 3.5 km from main points of consumption) to the Project. Early
indications are that the peak total water requirement for the Project will be approximately 294,711 m³/month.
Potable water will be sourced directly form the water supply scheme.

CAPITAL COST ESTIMATE

The capital cost estimate ("CCE") was principally compiled for the two declines, processing plant, process plant
infrastructure and other related infrastructure and covers all the costs associated with the construction and
associated expenditure required for an underground mining operation with a production capacity of 2.4Mtpa.

The estimate includes all costs associated with access; bulk services (power and water); surface and underground
mining infrastructure and facilities; process plant and supporting infrastructure, TSF, general supporting
infrastructure, and engineering procurement, construction management ("EPCM"). The study capital costs
estimates are assessed to have an accuracy of ±15 - 25%. Capital expenditure for the Project over the LoM is sub-
divided into mining, plant and shared infrastructure capital, as indicated in
Table 4.

The total initial capital for the Project, calculated as direct capital in years one to four (year when first metal is
produced), is estimated at ZAR6,456 million or USD330 million excluding contingencies and ZAR7,536 million or
USD385 million including contingencies.

Ongoing capital is defined as direct Project capital after year four, post plant construction and when production
started.

Stay in business capital or sustaining capital consists of renewals and replacement costs over the LoM.

A 20% contingency has been applied on all mining and shared infrastructure capital (initial and ongoing) and 15%
on plant and TSF capital.

                                              Table 4: Project Capital Expenditure

                      Capital Expenditure                                 ZARm                       USDm
                          Initial Capital
                      Direct Mining Capital                                          1,429                         73
                    Capitalised Development                                            449                         23
                           Plant Capital                                             2,519                        129
                            TSF Capital                                                820                         42
                  Shared Infrastructure Capital                                      1,240                         63
                           Contingency                                               1,079                         55
                       Total Initial Capital                                         7,536                        385

                        Ongoing Capital
                      Direct Mining Capital                                            693                         35
                    Capitalised Development                                            463                         24
                          Plant Capital                                                  -                          -
                           TSF Capital                                                 388                         20
                     Ongoing Shared Capital                                             42                          2
                          Contingency                                                  251                         13
                     Total Ongoing Capital                                           1,837                         94

                    Stay-in-Business Capital
                  Total Stay-in-Business Capital                                     9,171                        469

                                                                                                             
OPERATIONAL COST ESTIMATE

The Minxcon first-principles activity-based cost model was utilised to calculate operating costs for the
underground and the processing operations. The cost model utilises the mine and engineering design criteria and
production schedule inputs to derive cost rates for the mining, engineering and processing activities.

The costs for labour, equipment, consumables, services and utilities have been sourced from quotations, actual
industry stores costs, industry rates and utility rates. Where costs could not be obtained from these sources,
benchmarking with similar-sized projects and operations was conducted. The study operating costs estimates are
assessed to have an accuracy of ±15% - 25%. The operating cost summary is detailed in able 5 inclusive of
contingencies.

                                         Table 5: Operating Cost Summary

             Description                Total LoM           Per Milled t      6E Oz Recovered         % of AISC
                 Unit                  ZAR Million          ZAR/t                  ZAR/6E oz          %
                Mining                         52,007                1,149                6,893              44.0%
              Processing                       18,537                  410                2,457              15.7%
     Central & Technical Services              24,521                  542                3,250              20.8%
        Cash Operating Costs                   95,065                2,100               12,600              80.5%
               Royalties                       12,630                  279                1,674              10.7%
      Off-Mine Operating Costs                  1,154                   26                  153               1.0%
          Sustaining Capital                    9,171                  203                1,215               7.8%
            Rehabilitation                         80                    2                   11               0.1%
                 AISC                         118,099                2,609               15,653             100.0%
                
                 Unit                  USD Million          USD/t                 USD/6E oz            %
                Mining                          2,657                 58.7                  352              44.0%
              Processing                          947                 20.9                  126              15.7%
     Central & Technical Services               1,253                 27.7                  166              20.8%
        Cash Operating Costs                    4,857                107.3                  644              80.5%
               Royalties                          645                 14.3                   86              10.7%
      Off-Mine Operating Costs                     59                  1.3                    8               1.0%
          Sustaining Capital                      469                 10.4                   62               7.8%
            Rehabilitation                          4                  0.1                    1               0.1%
                 AISC                           6,034                133.3                  800             100.0%




                                                                                                       
FINANCIAL COST INDICATORS

Costs reported for the Project are displayed per milled tonne and per recovered 6E ounce in

Table 6. It should be noted that costs are inclusive of contingencies.

                           Table 6: Project Cost Indicators (Weighted Average over Life of Mine)

                    Description                            Unit                                Value
               Average Basket Price                      USD/6E oz                                                1,557
              Average Exchange Rate                      ZAR/USD                                                  19.57
                      Revenue                         ZAR/Milled tonne                                            4,831
                     Mine Cost                        ZAR/Milled tonne                                            1,149
                     Plant Costs                      ZAR/Milled tonne                                              410
                    Other Costs                       ZAR/Milled tonne                                              542
                      Royalties                       ZAR/Milled tonne                                              279
            Adjusted Operating Cost                   ZAR/Milled tonne                                            2,379
                  Sustaining Capex                    ZAR/Milled tonne                                              203
                   Rehabilitation                     ZAR/Milled tonne                                                2
                Off-Mine Overheads                    ZAR/Milled tonne                                               26
           All-in Sustaining Cost (AISC)              ZAR/Milled tonne                                            2,609
               Non-Sustaining Capex                   ZAR/Milled tonne                                              207
                 Non-Current Costs                    ZAR/Milled tonne                                                -
                  All-in Cost (AIC)                   ZAR/Milled tonne                                            2,816
                      EBITDA*                         ZAR/Milled tonne                                            2,425
                   EBITDA Margin                             %                                                      50%
                  4E oz Recovered                           oz                                                6,387,863
                      Revenue                            USD/4E oz                                                1,749
                     Mine Cost                           USD/4E oz                                                  416
                     Plant Costs                         USD/4E oz                                                  148
                    Other Costs                          USD/4E oz                                                  196
                      Royalties                          USD/4E oz                                                  101
            Adjusted Operating Cost                      USD/4E oz                                                  861
                  Sustaining Capex                       USD/4E oz                                                   73
                    Reclamation                          USD/4E oz                                                    1
                Off-Mine Overheads                       USD/4E oz                                                    9
           All-in Sustaining Cost (AISC)                 USD/4E oz                                                  945
               Non-Sustaining Capex                      USD/4E oz                                                   75
                 Non-Current Costs                       USD/4E oz                                                    -
                  All-in Cost (AIC)                      USD/4E oz                                                1,020
                       EBITDA                            USD/4E oz                                                  878
                  6E oz Recovered                           oz                                                7,544,915
                      Revenue                            USD/6E oz                                                1,481
                     Mine Cost                           USD/6E oz                                                  352
                     Plant Costs                         USD/6E oz                                                  126
                    Other Costs                          USD/6E oz                                                  166
                      Royalties                          USD/6E oz                                                   86
            Adjusted Operating Cost                      USD/6E oz                                                  729
                  Sustaining Capex                       USD/6E oz                                                   62
                    Reclamation                          USD/6E oz                                                    1
                Off-Mine Overheads                       USD/6E oz                                                    8
           All-in Sustaining Cost (AISC)                 USD/6E oz                                                  800
               Non-Sustaining Capex                      USD/6E oz                                                   63
                 Non-Current Costs                       USD/6E oz                                                    -
                  All-in Cost (AIC)                      USD/6E oz                                                  863
                       EBITDA                            USD/6E oz                                                  743


PROJECT POSITIONING

The Bengwenyama Project is estimated to be positioned in the lowest quartile of the PGM cost curve (R.
Hochreiter, 2024) as illustrated in Figure 8. The 6E All-In Sustaining Costs ("AISC") of the Project is estimated to
approximate those of Northam's Booysendal operation.
                                                                                                           
Figure 6: Bengwenyama Position on 6E Cost Curve

Source: Adapted from Rene Hochreiter (NOAH Capital Markets & Sieberana Research, 2024)

CASHFLOW

The Project capital expenditure, cash flow, and cumulative cash flow over the LoM are displayed in Figure 7,on an
annual basis in USD terms, respectively. The peak funding requirement is USD452 million (inclusive of
contingencies), with a pay-back period of 6.0 years from start of mining or 6.5 years from start of construction.

Figure 7: Annual and Cumulative Cash Flow - USD (Real Terms)
                                                                                                         
SENSITIVITY ANALYSIS

Based on the real cash flow calculated in the financial model, consultants and Minxcon performed single-
parameter sensitivity analyses to ascertain the impact on the NPV.

The bars represent various inputs into the model; each being increased or decreased by 15%. The left-hand side
of the graph indicates a negative 15% change in the input while the right-hand side of the graph indicating a
positive 15% change in the input.

A negative effect to the NPVs represented by red bars and a positive effect represented by blue bars. Exchange
rate, grade and PGM prices have the largest impact on the Project's NPV, followed by the mining operating costs.
The Project is least sensitive to the base metal prices, capital and processing operating costs.

Figure 8: Project Sensitivity USD (NPV8.0%)

Financial Investment Decision and Value Drivers

•   Commencement of feasibility study work to commence in early 2025 in parallel with project construction
    funding discussions with financiers leading to the Financial Investment Decision (FID).
•   Debt financing alternatives already progressed with the appointment of Blackbird Partners.
•   Feasibility critical path study work includes metallurgical and geotechnical assessments. Drilling required
    for both assessments to commence as soon as practicable, subject to statutory approvals.
•   Key value drivers in 2025 are the granting of the Mining Right, concentrate offtake outcomes and
    completion of a definitive feasibility study (DFS).

Submission of Mining Right Application (MRA)

On September 29, 2023, Southern Palladium officially submitted its application for a Mining Right (refer ASX
Announcement 2 October 2023). On 17 October 2023, the company received notification from the Department
of Mineral Resource and Energy (DMRE) that its application for the Mining Right has been accepted.
Comprehensive expert studies and consultations are ongoing, providing the foundation for a decision by the
DMRE anticipated early 2025.
                                                                                                           
Environmental Impact Assessment

To fulfill the environmental requirements for the Bengwenyama Project's Mining Right Application (MRA),
Southern Palladium submitted an Environmental Authorisation (EA) application to the DMRE. A full Scoping Study
was completed on February 14, 2024, followed by an Environmental Impact Assessment (EIA) process conducted
by OMI Solutions in accordance with EIA regulations.

The EIA report was submitted on July 10, 2024, and the DMRE issued an acknowledgment letter on July 22, 2024,
confirming the submission met core requirements for review.

Health And Safety

Southern Palladium is committed to upholding high standards of employee and workplace health and safety.
Exploration activities at Bengwenyama are conducted in compliance with all regulations including the South
African Mine Health and Safety Act (29 of 1996).

A comprehensive safety file, emergency response plan, policies and codes of practice are implemented,
incorporating key guidelines published by the Minerals Council South Africa (formerly called the Chamber of
Mines). Legal appointments are made in terms of policies and Mine Health and Safety regulations.

March 2025 Quarter Planned Activities

•  On-site project optimisation works will be included as part of the Final Investment Decision (FID). This work
   is expected to make project funding more attractive by either decreasing the ramp up period to full
   production or by decreasing the up-front capital requirement (or a combination of both).
•  The MRA (Mining Right Application) review process is expected to conclude early Q21 2025, with the Mining
   Right grant anticipated soon after.
•  Additional permit applications, including a Waste Management Licence (WML) and Water Use Licence (WUL),
   are underway.

Corporate

Appointment of Roger Baxter as Executive Chairman

During the quarter, Mr Roger Baxter as appointed as Executive Chairman of the Company. Mr Baxter was previously
appointed as a Director and Non-Executive Chairman on 1 January 2024 and has subsequently played a key role in
advancing the profile of the Company while overseeing proper and due governance at the Board level.

Mr Baxter's role as Executive Chairman will see him focussing on investor and government relations which
complements the role of Mr Johan Odendaal as Managing Director who is overseeing the more technical aspects of
advancing the Company's 70% interest in the Bengwenyama Project. The Bengwenyama Project is strategically
positioned in the heart of the world class Bushveld Complex in South Africa – the largest source of PGMs globally –
in a significant underground mining region with established expertise and infrastructure.

Expenditure Summary

A summary of the exploration and project evaluation expenditures for the quarter is provided as follows:

For the purpose of ASX Listing Rule 5.3.1, payments for exploration, evaluation and development during the quarter
totalled A$473,000 (30 September 2024: A$486,000). The Phase 1a and Phase 1b drilling programme, and facilities
set up and details of activities undertaken during the quarter are as described in this report.




                                                                                                           
            Table 7: Detailed summary of expenditure incurred for exploration, evaluation and development

                     Item                                   4Q24                                      3Q24
Assays & Analysis                                          1,266                                    21,338
Drilling                                                     -                                         -
Environmental, social and labour plan                     128,576                                  118,267
Exploration Management                                     51,686                                   71,770
Surface Right Usage                                        12,974                                   12,612
Technical Studies                                         278,525                                  261,579
Wireline Logging Services                                    -                                         -
Grand Total                                               473,027                                  485,566


For the purpose of ASX Listing Rule 5.3.2, the Company confirms there were no mining production and development
activities undertaken during the quarter.

For the purpose of ASX Listing Rule 5.3.5, payments to directors of Southern Palladium Limited during the quarter
totalled A$123,000. The payments were in respect of directors' salaries, fees and superannuation.

Payment to Minxcon Pty Ltd, a related party of two of the Company's Directors, Johan Odendaal and Daan van
Heerden, during the quarter totalled approximately A$274,000. The payments were in respect of expenses incurred
for management of the Bengwenyama Project.

Payment to Miracle Upon Miracle Investments (Pty) Limited, a related party of Southern Palladium Limited during
the quarter totalled approximately A$727,000. The payments were in respect of expenses incurred for the
Bengwenyama Project and corporate expenses.

Cash

As at 31 December 2024, Southern Palladium held approximately A$3.65 million (30 September 2024: A$4.73
million) in cash. This figure excludes cash held by the Company's 70% subsidiary, Miracle Upon Miracle Investments
(Pty) Limited at 31 December 2024 of A$0.43 million (30 September 2024: A$0.39 million).

December 2024 Quarter – ASX Announcements

This Report contains information extracted from ASX market announcements reported in accordance with the 2012
edition of the "Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves" ('2012
JORC Code'). Further details can be found in the following announcements lodged on the ASX:

8 October 2024        Roger Baxter takes on Executive Chairman role
23 October 2024       Bengwenyama Mineral Resource Update: Total (UG2 & MR) Mineral Resource now 40.25Moz
                      Merensky Reef Indicated Resource +17% to 2.23Moz (7E)
28 October 2024       Prefeasibility Study Results: Project NPV8 of USD1.059bn Maiden JORC Ore Reserve of 6.29 million oz @
                      6.17g/t PGM (6E)

JORC Competent Persons Statement

Uwe Engelmann
The information in this report that relates to Exploration Targets, Exploration Results and Mineral Resources is
based on information compiled by Mr Uwe Engelmann (BSc (Zoo. & Bot.), BSc Hons (Geol.), Pr.Sci.Nat. No.
400058/08, FGSSA). Mr Engelmann is a director of Minxcon (Pty) Ltd and a member of the South African Council
for Natural Scientific Professions. Minxcon provides geological consulting services to Southern Palladium Limited.
Mr. Engelmann has sufficient experience that is relevant to the style of mineralisation and type of deposit under
consideration and to the activity being undertaken to qualify as a Competent Person as defined in the 2012 Edition
of the 'Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves'.                                                                                                                
Mr. Engelmann consents to the inclusion in the report of the matters based on his information in the form and
context in which it appears. Mr Engelmann has a beneficial interest in Southern Palladium through a shareholding
in Nicolas Daniel Resources Proprietary Limited.

Daan van Heerden
The scientific and technical information contained in this announcement has been reviewed, prepared, and
approved by Mr Daan van Heerden (B Eng (Min.), MCom (Bus.Admin.), MMC, Pr.Eng. No. 20050318, AMMSA,
FSAIMM). Mr van Heerden is a director of Minxcon (Pty) Ltd and a Registered Professional Engineer with the
Engineering Council of South Africa, a Member of the Association of Mine Managers South African Council, as well
as a Fellow Member of the South African Institute of Mining and Metallurgy. Mr. van Heerden has sufficient
experience relevant to the styles of mineralisation and activities being undertaken to qualify as a Competent
Person, as such term is defined in the 2012 Edition of the 'Australasian Code for Reporting of Exploration Results,
Mineral Resources and Ore Reserves'. Mr. van Heerden consents to the inclusion in the report of the matters
based on his information in the form and context in which it appears. Mr van Heerden has a beneficial interest in
Southern Palladium through a shareholding in Nicolas Daniel Resources Proprietary Limited.

This announcement has been approved for release by the Board of Southern Palladium Limited.

For further information, please contact:
Johan Odendaal
Managing Director, Southern Palladium
Phone: +27 82 557 6088
Email: johan.odendaal@southernpalladium.com

JSE Sponsor
Merchantec Capital


Media & investor relations inquiries: Sam Jacobs, Six Degrees Investor Relations: +61 423 755 909
                                                                                                           
Appendix 1

Tenements

The Company held the following tenement during the quarter. The Project comprises the full extent of the farms
Nooitverwacht 324 KT and Eerstegeluk 327 KT, both of which are in the Limpopo Province of South Africa. The
Project is located 250 km east-northeast of Pretoria. The tenement is 100% held through Miracle Upon Miracle
(Pty) Ltd, the 70% subsidiary of SPD. On September 29, 2023, Southern Palladium submitted its application for a
Mining Right (refer ASX Announcement 2 October 2023 - Bengwenyama Project Mining Right Application
Submitted), which received official acceptance on 17 October 2023 from the Department of Mineral Resource
and Energy (DMRE). This marked the commencement of the official consideration of the Mining Right Application
and of the Environmental Impact Assessment and expert studies, which are currently underway.

The Company did not enter into any farm-in or farm-out agreements during the quarter.

The following information is provided pursuant to Listing Rule 5.3.3 for the quarter:

                                                    Interest at beginning of quarter    Interest at end of quarter
 Farm name                    Extent (ha)
 Nooitverwacht 324 KT                   2,971.01
 Eerstegeluk 327 KT                     2,308.73                   70%                             70%
 Total                                  5,279.74

No tenement has been disposed during the quarter.




                                                                                                         
Appendix 2
Mineral Resource

The total combined Mineral Resource for the UG2 and MR as at 23 October 2024 is summarised in Error! Reference source
not found..

                                               Table 8: Combined UG2 and MR Mineral Resource as at 23 October 2024

                                  Tonnes Thickness            Pt       Pd      Rh    Au         Ir           Os           Ru        4E     7E     Cu            Ni
               Resource                                                                                                                                                Moz     Moz       Total
  Reef                             Mt             (m)                                        (g/t)                                                       (%)
               Category                                                                                                                                                (4E)    (7E)       Moz1
Merensky        Indicated         25.11           2.02       1.62     0.64    0.10   0.12     0.03           0.03        0.21      2.49   2.76    0.04         0.12    2.01    2.23       2.23
Merensky      Inferred (7E)       62.54           1.81       2.09     0.86    0.14   0.18     0.04           0.04        0.26      3.22   3.55    0.05         0.14    6.47    7.13       7.13
Merensky       Total (7E)         87.66           1.87       1.96     0.80    0.13   0.16     0.04           0.04         0.24     3.01   3.32    0.04         0.13    8.48    9.36       9.36
Merensky      Inferred (4E)       59.44           1.96       2.01     0.93    0.10   0.17                                          3.18                                6.08               6.08
Merensky       Total (4E)     147.10              1.90       1.98     0.85    0.11   0.17                                          3.08                                14.56             15.44
  UG2          Measured           7.17            0.77       3.69     3.75    0.76   0.12     0.25           0.17        1.24      8.34   10.00   0.03         0.16    1.92    2.30        2.3
  UG2           Indicated         18.52           0.72       3.68     3.63    0.76   0.11     0.26           0.17        1.23      8.19   9.85    0.04         0.16    4.88    5.86       5.86
  UG2         Inferred (7E)       33.01           0.69       3.67     3.50    0.76   0.11     0.26           0.17        1.23      8.04   9.70    0.04         0.17    8.54    10.30      10.3
  UG2          Total (7E)         58.70           0.71       3.67     3.57    0.76   0.11     0.26           0.17         1.23     8.12   9.78    0.04         0.17    15.33   18.46     18.46
  UG2         Inferred (4E)       36.12           1.30       3.00     2.01    0.44   0.07                                          5.47                                6.35               6.35
  UG2          Total (4E)         94.82           0.93       3.42     2.98    0.64   0.10                                          7.11                                21.68             24.81
   Combined Total (7E)        146.35              1.40       2.64     1.91    0.38   0.14     0.13           0.09         0.64     5.06   5.91    0.04         0.14    23.81   27.82
   Combined Total (4E)        241.92              1.52       2.54     1.68    0.32   0.14                                          4.66                                36.24
 Combined Total (7E&4E)1                                                                                                                                                                 40.25
        
              Note:
              5. Several historic drill holes in the Nooitverwacht Extension area did not assay for the minor PGEs, so a 7E resource cannot yet be stated
                 for part of the inferred Mineral Resource. However, it does contribute to the total resource ounces.
              6. All elements have been estimated individually and their combined grade will vary slightly from the estimated composite 4E and 7E
                 modelled grades.

              Note:
              7. Several historic drill holes in the Nooitverwacht Extension area did not assay for the minor PGEs, so a 7E resource cannot yet be stated
                 for part of the inferred Mineral Resource. However, it does contribute to the total resource ounces.
              8. All elements have been estimated individually and their combined grade will vary slightly from the estimated composite 4E and 7E
                 modelled grades.


Mineral Reserve
The 6E Ore Reserves for the Project consist of Measured and Indicated Resources from the UG2 reef only. The
Ore Reserve classification was conducted by converting Measured and Indicated Mineral Resources to Probable
Ore Reserves.

Table 2 provides a detailed summary of the tonnage, grades and content for Probable Ore Reserves within the
Bengwenyama Project.

                                                   Table 9: Ore Reserve Estimation as at 23 October 2024 (UG2 reef)

                                     Tonnes         Pt     Pd        Rh      Au       lr              Os            Ru           4E        6E     Cu       Ni     Cr203   Moz(6E)
           Ore Reserve Category
                                          Mt       (g/t)   (g/t)    (g/t)    (g/t)   (g/t)           (g/t)        (g/t)          (g/t)    (g/t)   (%)      (%)     (%)
                Probable                  31.72     2.34    2.33    0.48      0.07    0.16              -           0.78          5.22    6.17    0.02     0.12   19.03    6.29
                 Total                    31.72     2.34    2.33    0.48      0.07    0.16              -           0.78          5.22    6.17    0.02     0.12   19.03    6.29
     Notes:
       4. The Ore Reserve estimation included diluted Measured and Indicated Mineral Resources only.
       5. No Inferred Mineral Resources have been included in the Ore Reserve.
       6. The Ore Reserve estimation was completed using a 6E basket price (before payabilities) of USD1,557/oz over the LoM.
                                                                                                                                                                               
Platinum Group Minerals (PGMs) within the Bushveld Complex exhibit varying ratios (referred to as the Prill Split), with
platinum (Pt), palladium (Pd), and rhodium (Rh) constituting the predominant components. Additionally, other PGMs such as
ruthenium (Ru), iridium (Ir), and osmium (Os) are also present, although in smaller quantities. These ratios exhibit variations
from one section of the complex to another. Notably, the UG2 reef at the Bengwenyama project represents an even
distribution of Platinum and Palladium, accompanied by a notable concentration of Rhodium. Conversely, the Merensky Reef
is characterized by a high platinum content.

Figure 9: Platinum Group Metals + Gold Prill Split                      Figure 10: Project Stratigraphic Column

                                                                                                                      
Appendix 5B
Mining exploration entity or oil and gas exploration
entity
quarterly cash flow report

Name of entity
Southern Palladium Limited

ABN                                                                Quarter ended ("current quarter")
59 646 391 899                                                                 31-Dec-24

Consolidated statement of cash flows                                 Current         Year to date
                                                                     quarter         (6 months)
                                                                     $A'000            $A'000
1     Cash flows from operating activities
1.1   Receipts from customers                                            -                   -
1.2   Payments for
      (a) exploration & evaluation
      (b) development                                                     -                  -
      (c) production                                                      -
      (d) staff costs                                                   (65)               (173)
      (e) administration and corporate costs                           (313)               (622)
1.3   Dividends received (see note 3)
1.4   Interest received                                                 31                  89
1.5   Interest and other costs of finance paid
1.6   Income taxes paid
1.7   Government grants and tax incentives
1.8   Other - Miracle Upon Miracle Pty Ltd operating expenditure       (254)               (115)
1.9   Net cash from / (used in) operating activities                   (601)               (821)

2     Cash flows from investing activities
2.1   Payments to acquire or for:
      (a) entities
      (b) tenements
      (c) property, plant and equipment
      (d) exploration & evaluation                                     (473)               (959)
      (e) investments
      (f) other non-current assets
2.2   Proceeds from the disposal of:
      (a) entities
      (b) tenements
      (c) property, plant and equipment
      (d) investments
      (e) other non-current assets
2.3   Cash flows from loans to other entities
2.4   Dividends received (see note 3)                                                        
2.5   Other                                                              -                   -
2.6   Net cash from / (used in) investing activities                   (473)               (959)


                                                                                                   
                                                                                                              Current            Year to date
Consolidated statement of cash flows                                                                          quarter            (6 months)
                                                                                                              $A'000               $A'000
3      Cash flows from financing activities
3.1    Proceeds from issues of equity securities (excluding convertible debt
       securities)
3.2    Proceeds from issue of convertible debt securities
3.3    Proceeds from exercise of options
3.4    Transaction costs related to issues of equity securities or convertible
       debt securities
3.5    Proceeds from borrowings
3.6    Repayment of borrowings
3.7    Transaction costs related to loans and borrowings
3.8    Dividends paid
3.9    Other
3.1    Net cash from / (used in) financing activities                                                             -                       -

4      Net increase / (decrease) in cash and cash equivalents for
       the period
4.1    Cash and cash equivalents at beginning of period                                                        4,725                   5,431
4.2    Net cash from / (used in) operating activities (item 1.9 above)                                         (601)                   (821)
4.3    Net cash from / (used in) investing activities (item 2.6 above)                                         (473)                   (959)
4.4    Net cash from / (used in) financing activities (item 3.10 above)                                          -                       -
4.5    Effect of movement in exchange rates on cash held
4.6    Cash and cash equivalents at end of period                                                              3,651                   3,651

5      Reconciliation of cash and cash equivalents                                                            Current               Previous
                                                                                                              quarter               quarter
       at the end of the quarter (as shown in the consolidated statement of                                   $A'000                $A'000
       cash flows) to the related items in the accounts
                                                                                                                                 
5.1    Bank balances                                                                                            251                   725
5.2    Call deposits                                                                                           3,400                 4,000
5.3    Bank overdrafts
5.4    Other (provide details)
5.5    Cash and cash equivalents at end of quarter (should equal
       item 4.6 above)                                                                                         3,651*                 4,725
       
       * NOTE: This figure excludes cash held by the Company's related party, Miracle Upon Miracle Investments (Pty) Limited at 31 December 2024 of
       A$0.43 million (30 September 2024: A$0.39 million).

6      Payments to related parties of the entity and their                                                                           Current
       associates                                                                                                                    quarter
                                                                                                                                     $A'000
6.1    Aggregate amount of payments to related parties and their associates
       included in item 1                                                                                                              123       
6.2    Aggregate amount of payments to related parties and their associates
       included in item 2                                                                                                              274
       
Note: if any amounts are shown in items 6.1 or 6.2, your quarterly activity report must include a description of, and an explanation for, such
payments.
A total approximately of $397,000 was paid to related parties of the entities and their associates as follow:
- $123,000 are in respect of Directors' fees, salaries and superannuation accruing to Directors' for services rendered during the period.
- $274,000 was paid to Minxcon Pty Ltd for project management of the Bengwenyama Project. Two of the Company's Directors, Johan
  Odendaal and Daan van Heerden, are significant and controlling shareholders in Minxcon.

                                                                                                                                                    
7     Financing facilities                                                                           Total facility              Amount
      Note: the term "facility' includes all forms of financing arrangements available to the         amount at                  drawn at
      entity.                                                                                        quarter end                quarter end
      Add notes as necessary for an understanding of the sources of finance available to the           $A'000                     $A'000
      entity.

7.1   Loan facilities
7.2   Credit standby arrangements
7.3   Other (please specify)
7.4   Total financing facilities                                                                         -                         -

7.5   Unused financing facilities available at quarter end                                                                         -
                                                                                                                                   
7.6 
      Include in the box below a description of each facility above, including the lender, interest rate, maturity date
      and whether it is secured or unsecured. If any additional financing facilities have been entered into or are
      proposed to be entered into after quarter end, include a note providing details of those facilities as well.




8     Estimated cash available for future operating activities                                                                    $A'000

8.1   Net cash from / (used in) operating activities (item 1.9)                                                                    (601)
8.2   (Payments for exploration & evaluation classified as investing activities)
      (item 2.1(d))                                                                                                                (473)
8.3   Total relevant outgoings (item 8.1 + item 8.2)                                                                              (1,074)
8.4   Cash and cash equivalents at quarter end (item 4.6)                                                                          3,651
8.5   Unused finance facilities available at quarter end (item 7.5)                                                                  -
8.6   Total available funding (item 8.4 + item 8.5)                                                                                3,651

8.7   Estimated quarters of funding available (item 8.6 divided by
      item 8.3)                                                                                                                     3.4
      Note: if the entity has reported positive relevant outgoings (ie a net cash inflow) in item 8.3, answer item 8.7 as
      "N/A". Otherwise, a figure for the estimated quarters of funding available must be included in item 8.7.

8.8   If item 8.7 is less than 2 quarters, please provide answers to the following questions:
      8.8.1 Does the entity expect that it will continue to have the current level of net operating
      cash flows for the time being and, if not, why not?
      Answer: N/A

      8.8.2 Has the entity taken any steps, or does it propose to take any steps, to raise further
      cash to fund its operations and, if so, what are those steps and how likely does it believe
      that they will be successful?
      Answer: N/A

      8.8.3 Does the entity expect to be able to continue its operations and to meet its
      business objectives and, if so, on what basis?
      Answer: N/A

      Note: where item 8.7 is less than 2 quarters, all of questions 8.8.1, 8.8.2 and 8.8.3 above must be answered.
                                                                                                                                            
Compliance statement

1     This statement has been prepared in accordance with accounting standards and policies which comply with
      Listing Rule 19.11A.

2     This statement gives a true and fair view of the matters disclosed.

Date: 31 January 2025

Authorised by: The Audit Committee
(Name of body or officer authorising release – see note 4)


Notes

1       This quarterly cash flow report and the accompanying activity report provide a basis for informing the market about the entity's activities
        for the past quarter, how they have been financed and the effect this has had on its cash position. An entity that wishes to disclose
        additional information over and above the minimum required under the Listing Rules is encouraged to do so.

2       If this quarterly cash flow report has been prepared in accordance with Australian Accounting Standards, the definitions in, and
        provisions of, AASB 6: Exploration for and Evaluation of Mineral Resources and AASB 107: Statement of Cash Flows apply to this
        report. If this quarterly cash flow report has been prepared in accordance with other accounting standards agreed by ASX pursuant to
        Listing Rule 19.11A, the corresponding equivalent standards apply to this report.

3       Dividends received may be classified either as cash flows from operating activities or cash flows from investing activities, depending on
        the accounting policy of the entity.

4       If this report has been authorised for release to the market by your board of directors, you can insert here: "By the board". If it has been
        authorised for release to the market by a committee of your board of directors, you can insert here: "By the [name of board committee –
        eg Audit and Risk Committee]". If it has been authorised for release to the market by a disclosure committee, you can insert here: "By
        the Disclosure Committee".

5       If this report has been authorised for release to the market by your board of directors and you wish to hold yourself out as complying
        with recommendation 4.2 of the ASX Corporate Governance Council's Corporate Governance Principles and Recommendations, the
        board should have received a declaration from its CEO and CFO that, in their opinion, the financial records of the entity have been
        properly maintained, that this report complies with the appropriate accounting standards and gives a true and fair view of the cash flows
        of the entity, and that their opinion has been formed on the basis of a sound system of risk management and internal control which is
        operating effectively.




                                                                                                                                                

Date: 31-01-2025 09:30:00
Produced by the JSE SENS Department. The SENS service is an information dissemination service administered by the JSE Limited ('JSE'). 
The JSE does not, whether expressly, tacitly or implicitly, represent, warrant or in any way guarantee the truth, accuracy or completeness of
 the information published on SENS. The JSE, their officers, employees and agents accept no liability for (or in respect of) any direct, 
indirect, incidental or consequential loss or damage of any kind or nature, howsoever arising, from the use of SENS or the use of, or reliance on,
 information disseminated through SENS.